Quantities

Concrete / trench quantity

Vnet=lbdVorder=Vnet(1+w100)
where
Vnet
net concrete volume (m³)
l
length (m)
b
width (m)
d
depth (m)
Vorder
volume to order (m³)
w
allowance (%)
Explain this equation

This gives the volume of concrete for a rectangular strip footing or trench fill, and the volume to order with an allowance.

l is the length, b the width and d the depth of the trench, all in metres. V_net is the net volume of concrete in m³. w is the allowance percentage for over-dig and wastage, and V_order is the amount to order.

Volume is length times width times depth. Multiplying by (1 + w/100) adds the allowance.

A 10 m trench 600 mm wide and 300 mm deep holds 1.8 m³. With 5% allowance, order 1.89 m³. Doubling the depth doubles the concrete.

Watch out: trenches are rarely perfect. Measure the actual dig; this does not design the foundation.

Calculate volume for a rectangular strip and an ordering allowance.

m
m
m
%

Enter your values to see the result.

Good to know

All dimensions in metres. Measure excavation variations; this does not design foundation width, depth, reinforcement or bearing capacity.