Tradefox

Tradefox – Build Skills

Learn Construction

‹ All bricklaying calculators

Quantities

Excavation & loose spoil

Vin situ=LWDVloose=Vin situk
where
Vin situ
in-situ (bank) volume (m³)
L
length (m)
W
width (m)
D
depth (m)
Vloose
loose volume (m³)
k
bulking factor
Explain this equation

This gives the volume of soil dug out and how much space it will take up once loosened. Use it for planning skips, muck-away or stockpile space.

L, W and D are the length, width and depth of the excavation in metres. V_in situ is the volume of undisturbed ground. k is the bulking factor: how many times larger the soil becomes once dug. V_loose is the loose volume.

Dug soil takes up more room than in the ground because air fills the gaps between broken lumps. The bulking factor multiplies the in-situ volume to allow for that.

A 10 m trench 600 mm wide and 1 m deep is 6 m³ in the ground. With a factor of 1.3 that becomes 7.8 m³ of loose spoil.

Watch out: the factor depends on the soil. Skips are often limited by weight, not just volume.

Apply an estimated bulking factor to in-situ excavation.

m
m
m

Enter your values to see the result.

Good to know

Use a soil-specific factor. Loose volume does not establish skip payload; check mass and waste rules separately.

Sources

  • Geometry / arithmetic

Estimates are not design approval or British Standards compliance checks. Structural arch, retaining-wall, wind, foundation, lintel and masonry-capacity design are not performed. Use the project engineer’s specification.