Site maths

Labour duration

Dw=UrDt=Dwp
where
Dw
worker-days
U
units to lay
r
rate (units per person-day)
Dt
team-days
p
number of people
Explain this equation

This gives a rough labour duration from the number of units to lay, a production rate and the size of the team.

U is the number of units to lay. r is the rate one person lays in a day. D_w is the total worker-days. p is the number of people, and D_t is the number of days the team takes.

Dividing the work by the daily rate gives the total effort in worker-days. Sharing that effort between p people gives the calendar working days, assuming everyone works at the same rate.

1200 bricks at 400 per person-day is 3 worker-days, or 1.5 days for two people. Doubling the team halves the days, in theory.

Watch out: access, weather, cutting, curing and preparation all slow production. Fractional days are kept, so round up as the job requires.

Estimate working time using a realistic team rate.

Enter your values to see the result.

Good to know

Fractional days are retained. Access, complexity, curing, weather and preparation affect production. This is not a promised programme.

Sources

  • Geometry / arithmetic

Estimates are not design approval or British Standards compliance checks. Structural arch, retaining-wall, wind, foundation, lintel and masonry-capacity design are not performed. Use the project engineer’s specification.