[language-switcher]
[wpdreams_ajaxsearchlite]

RFI In Construction: What It Is, When To Use It, And Sample Requests

In construction, small mistakes can quickly become big delays or cost disputes. That’s where the RFI (Request for Information) comes in, a formal, traceable tool that keeps design intent and site execution aligned.

Though often seen as paperwork, RFIs are one of the sharpest tools in a project manager’s kit. Used correctly, they keep project clarity, protect against claims, and keep everyone, from subcontractors to consultants, on the same page.

Let’s break down what an RFI is, when to issue one, what to include, and how it’s managed under UK contracts like JCT and NEC.

What Is An RFI In Construction?

An RFI (Request for Information) is a formal written query raised by one party on a construction project (usually a contractor or subcontractor) seeking clarification or additional details about the design, specification, or contract documents.

Essentially, it’s a way of saying: “We need more detail before we can proceed without risk or error.”

RFIs can be about:

It’s not to shift blame or create extra admin, it’s to ensure every part of the build is done correctly, safely, and per design intent.

Why RFIs Matter In UK Construction Projects

UK projects operate within strict frameworks like CDM Regulations 2015 and Building Safety Act 2022, where communication and traceability are critical.

A well-managed RFI system:

In short, every RFI is a form of protection and accountability for both sides.

When To Raise An RFI?

An RFI should be raised whenever information is:

The golden rule?

 If the lack of clarity could impact quality, cost, or programme, it’s worth an RFI.

However, excessive or vague RFIs can frustrate the design team. Always be specific, concise, and link to the relevant drawing, clause, or spec reference.

The RFI Process Step-By-Step

Different projects and software platforms (like Aconex, Viewpoint, or Procore) have their own formats, but the process generally follows this sequence:

1. Identify The Issue

Review drawings, specs, or site conditions. Note any missing, unclear, or conflicting information. Take photos or mark-up drawings if helpful.

2. Draft The RFI

Make sure you work on the RFI so that it may include:

Submit To The Correct Party

Usually, RFIs go from contractor → design team or subcontractor → main contractor. Ensure you follow the project’s document control procedure or software workflow.

Await For The Response

Responses should be timely, typically within 7 to 14 days, depending on contract terms. Some contracts require a formal RFI register to track status.

Record And Distribute

Once a reply is received, log it, update the register, and share with affected trades or teams. If the answer leads to changes, ensure it’s captured in the variation or design change record.

Visual Vs.Technical RFIs

Type Example Purpose
Clarification RFI Conflicting Dimensions Between
Plan And Section
Seeks Design Clarification
Confirmation RFI Approval Of Alternative Product Requests Client Or Designer
Sign-off
Site Condition RFI Obstruction Found During Excavation Alerts to Unforeseen Issue

Understanding which type you’re issuing ensures the right person, architect, structural engineer, or client receives it and responds promptly.

RFIs Under JCT Vs NEC Contracts

While both JCT and NEC contracts allow for RFIs, they handle communication and responsibility differently.

Under JCT Contracts

Under NEC Contracts

So in short:

JCT = more document-based, NEC = more communication-based, but both benefit from a robust RFI trail.

What ‘Competent’ Means In Handling RFIs

The person raising or responding to an RFI should be competent, meaning they understand the technical, safety, and contractual implications of the question.

For example:

Competence isn’t just about job title, it’s about understanding what’s being asked and the potential impact of the answer.

Common RFI Mistakes (And How to Avoid Them)

cranes-construction-site

Even experienced teams get this wrong. A few classic pitfalls:

1. Vague Questions

 “Please confirm wall build-up” isn’t helpful. Be specific: “Please confirm insulation thickness for wall type W1, conflicting between GA-01 and Detail D2.”

2. Late Submissions

Don’t wait until you’re on-site with materials arriving. Anticipate information needs during planning and procurement.

3. Poor Tracking

Unlogged RFIs vanish. Use a digital RFI register with status columns (Raised, Responded, Closed).

4. Using RFIs as Leverage

Avoid raising RFIs as negotiation tools. It damages trust and slows responses.

5. Missing Attachments

A marked-up drawing can save ten back-and-forth emails. Visuals clarify faster than text.

What Evidence To Keep?

In a dispute or claim, RFIs are part of the project record. You should retain:

Digital systems like Viewpoint, Aconex, or Field View allow exporting audit trails, an invaluable defence if something later goes wrong.

Sample RFI Template (UK Format)

Field Example Entry
RFI No. RFI-023
Project ST. Mary’s School Extension
Raised By Main Contractor
Date Raised 07/10/2025
Drawing Ref. S-104, GA-201
Subject Clarification On Steel Beam Bearing Detail
Query Please confirm the bearing length of beam B12. Detail D4 shows 150mm,
GA-201 shows 100mm.
Attachments Marked-up PDF, site photo
Response Due 14/10/2025
Response By Structural Engineer
Reply Beam B12 to have a 150mm bearing as per Detail D4. GA-201 to be
amended.

Why RFIs Reflect Professionalism

RFIs are more than admin, they demonstrate a contractor’s discipline and professionalism. A clean, precise RFI record shows clients and consultants that your team works methodically, communicates clearly, and protects the integrity of the build.

Well-documented RFIs can also protect cash flow by supporting extension-of-time claims or variation requests later on.

Bottom Line

In UK construction, RFIs keep communication watertight. They help bridge the gap between design intent and site reality, protecting timelines, budgets, and reputations.

Handled poorly, they become a bottleneck. Managed well, they’re proof of control, competence, and professionalism.

So whether you’re managing a housing development or a complex M&E package, make RFIs part of your daily routine, clear, concise, and traceable.

For professionals wanting to practise communication workflows in a risk-free environment, tools like Tradefox let you simulate raising and responding to RFIs before applying them to real projects.

SHARE ARTICLE

You may also like...

Latest news and articles, direct from Tradefox.

Secret Link