Site maths

Labour duration

Dw=UrDt=Dwp
where
Dw
worker-days
U
items / work units
r
work units per person-day
Dt
team working days
p
people
Explain this equation

Estimates how long a task will take from the amount of work, a realistic output rate and the size of the team.

U is the amount of work, in whatever unit suits: items, metres or square metres. r is how many of those units one person completes in a day. Dw is the total effort in worker-days. p is the number of people, and Dt is the elapsed working days for the team.

Dividing the work by the daily rate gives the total effort. Sharing that effort across p people divides the elapsed time by p, assuming everyone works at the same rate.

120 units at 40 per person-day is 3 worker-days; with two people that is 1.5 days.

Watch out: doubling the team rarely halves the time in practice. Access, setting out, drying times and weather all slow output.

Estimate working time using a realistic team rate.

Enter your values to see the result.

Good to know

Fractional days are retained. Access, complexity, curing, weather and preparation affect production. This is not a promised programme.